This project, in the Highland Park neighborhood of the City of Pittsburgh, will replace approximately 550 feet of aging water main, providing more reliable water service to our customers. This site was scheduled for replacement after several water main breaks occurred over the past year. As part of the main replacement, we will replace all public water service lines, including lead water service lines, with a non-lead material.
Progress & Status
- New water main and service lines have been installed.
- Street restoration is complete.
Locations & Schedule
Start Date: May 2020
Completion Date: August 2020
Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.
Traffic Patterns: The street will be closed to local traffic during working hours and will be plated and re-opened at the end of the work day. We recommend residents park on N. Euclid Avenue.