Street and Sidewalk Restoration Schedule

In Construction Water

After we complete a water or sewer repair, we must then come back and repave or re-concrete the area we impacted as part of our work. This multi-million dollar effort improves streets and sidewalks throughout our service area as a result of our work underground.

We are responsible for asphalt and concrete replacement after emergency water and sewer repairs or infrastructure upgrade projects. When a job is complete, the location is given to the restoration contract, which sends asphalt, concrete, and line painting crews out to restore the area to its former condition. When work happens on your street, it may be a few weeks until paving and concrete crews return. Crews move in an orderly fashion around our service area completing work, focusing on all the locations in one area before moving onto the next.

Percentage completion on this project refers to the total number of sites addressed as part of this construction contract and does not reference to the total number of PWSA restoration sites completed over time.

Progress & Status

18%
Construction Complete

The street and sidewalk restoration locations for July 3rd are as follows:

Addison Street at Hemans Street 5014 Stanton Avenue
5031 Somersville Street 970 Oramore Street
4928 Somerville Street 5155 Hillcrest Street
928 Woodbine Street Alpine and Arch Street
4309 Stanton Avenue 258 Carrington Street
5557 McCandless Avenue 1012 Abedll Street
5327 McCandless Avenue 1102 Galveston Street
5268 Wickliff Street N. Franklin Street at Bidwell Street
5248 Carnegie Street 915 Behan Street
5410 Carnegie Street 1118 Decatour Street
4601 Plummer Street 1336 Pennslyvania Avenue
180 46th Street 2034 Chateau Street
240 46th Street 1501 Preble Avenue
4615 Carlton Street Reedsdale Street at Scottdale Avenue
807 Leydon Street Lysle Street at A Street
5268 Wickliff Street 929 Kirkbride Street
5222 Wickliff Street 713 Melrose Avenue
4267 Stanton Avenue 1816 A Street

 

 

work is weather-dependent and subject to change

Locations & Schedule

Location Details:
Throughout service area

Start Date: Ongoing

Completion Date: Ongoing, with pauses during cold weather

Work Schedule: 7:00 am - 5:00 pm, M-F

Traffic Patterns: Street closures and no parking may be necessary to complete paving work.

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin

mmclaughlin@pgh2o.com