PWSA PAVING SCHEDULE
September 24 – September 28, 2018

Pittsburgh, PA - The Pittsburgh Water and Sewer Authority (PWSA) contractors are scheduled to complete surface restoration, which includes paving and concrete work for the week of September 24, 2018. Many work locations will require restricted parking while work is being performed. Signs will be posted in advance and removed as soon as possible.

 

*Please note that the schedule is weather dependent and subject to change.

 

Work locations are as follows:

 

3253 Ward Street
11 Boulevard of the Allies
3631 Childs Street
50 Boulevard of the Allies
3731 Childs Street
329 Boulevard of the Allies
130 Augustine Street
5281 Forbes Avenue
Kaercher Street at Bristol Street
Forbes Avenue at Margaret Morrison Street
6600 Frankstown Avenue
5147 Forbes Avenue
6505 Shetland Street
714 Shady Avenue
541 Lowell Street
402 Ruxton Street
6431 Shetland Street
423 Ruxton Street
Winfield Street at Shetland Street
437 Ruxton Street
616 North Sheridan Avenue
471 Ruxton Street
1114 Winterton Street
30 Craighead Street
1458 North Highland Avenue
40 Craighead Street
Tabor Street at Stafford Street
45 Craighead Street
327 Stadium Street
59 Craighead Street
114 Sanford Street
 
Sanford Street Field Way
 
Esplen Street at Sanford Street
 
Esplen Street at Cheery Way
 
3100 Esplen Street

 

 

 