Small Diameter Sewer Reconstruction Project

In Construction Sewer

This project in the Overbrook neighborhood of the City of Pittsburgh, will line several miles of aging sewers, repair broken sewers, relocate storm drains, and separate combined storm and sanitary sewers where needed. Work will be completed at numerous locations throughout the neighborhood and residents will be notified when work may impact them. Lining and repairing these sewers will extend the life of the sewer system and ensure better service to our customers.

Progress & Status

55%
Construction Complete

Sewer lining work continues throughout area. Customers will be notified of work via door hangers.

Locations & Schedule

Location Details:
Locations throughout Carrick neighborhood

Start Date: Summer 2020

Completion Date: Summer 2021

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin
412-255-8945
mmclaughlin@pgh2o.com