Water Main Replacment Project - Brighton Heights Phase II

In Construction Water

This project, in the Brighton Heights neighborhood of the City of Pittsburgh, will replace water mains on several streets, providing more reliable water service to our customers.

Progress & Status

7%
Construction Complete

Service line inspections and water main installation are ongoing throughout the project area. 

Work will occur on the following streets, in approximately this order: 

  • Davis Avenue
  • California Avenue
  • Fairlee Street
  • Falck Avenue
  • Rankin Avenue
  • Massachusetts Avenue
  • Fleming Avenue
  • McClure Avenue
  • Gass Avenue
  • Beckham Street
  • Shadeland Avenue
  • Gerber Avenue
  • Simen Avenue
  • Etola Street
  • Corona Street
  • Antrim Street
  • Richardson Avenue
  • Hybla Street

 

Locations & Schedule

Start Date: Summer 2025

Completion Date: Spring 2026

Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.

Traffic Patterns: The street will be closed to local traffic during working hours and will be plated and re-opened at the end of the work day.