10th Street Road Restoration

Completed Water

This work is a result of a large sinkhole that collapsed in late October 2019, damaging underlying infrastructure, one Port Authority Transit bus, and a vehicle. The street has been closed to pedestrian and car traffic to-date. Street restoration work will be done under a cost-share agreement with the City of Pittsburgh, who will share in the final cost of restoration of the street.

Progress & Status

100%
Construction Complete
  • PWSA construction work is complete.
  • The road will be reopened to traffic after other utility work in the area is complete.

Locations & Schedule

Location Details:
Downtown Pittsburgh

Start Date: May 18, 2020

Completion Date: July 10, 2020

Work Schedule: 7:00 a.m. - 4:00 p.m., Monday-Friday

Traffic Patterns: Street will remain closed to traffic until work is completed.

10th street restoration

10th Street (Penn Avenue - Liberty Avenue)
Pittsburgh, PA 15222
United States