Street and Sidewalk Restoration Schedule

In Construction Water

After we complete a water or sewer repair, we must then come back and repave or re-concrete the area we impacted as part of our work. This multi-million dollar effort improves streets and sidewalks throughout our service area as a result of our work underground.

We are responsible for asphalt and concrete replacement after emergency water and sewer repairs or infrastructure upgrade projects. When a job is complete, the location is given to the restoration contract, which sends asphalt, concrete, and line painting crews out to restore the area to its former condition. When work happens on your street, it may be a few weeks until paving and concrete crews return. Crews move in an orderly fashion around our service area completing work, focusing on all the locations in one area before moving onto the next.

Percentage completion on this project refers to the total number of sites addressed as part of this construction contract and does not reference to the total number of PWSA restoration sites completed over time.

Progress & Status

18%
Construction Complete

The street and sidewalk restoration locations for July 2nd are as follows:

Addison Street at Hemans Street 4267 Stanton Avenue
27 McCandless Avenue 5014 Stanton Avenue
118 N. Mathilda Street 970 Oramore Street
4913 Dearborn Street 5155 Hillcrest Street
5223 Jordan Way (On Kincaid Street) Alpine Street at Arch Street
5170 Hillcrest Street 258 Carrington Street
322 Azure Street (Rear on Schenley Manor Drive) 1012 Abedll Street
5143 Rosecrest Drive 1102 Galveston Street
5168 Rosecrest Drive N. Franklin Street at Bidwell Street
265 Schenley Manor Drive 915 Behan Street
956 Oranmore Street 1118 Decatour Street
959 Oranmore Street 1336 Pennslyvania Avenue
970 Oranmore Street 2034 Chateau Street
146 44th Street 1501 Preble Avenue
5248 Carnegie Street Reedsdale Street at Scottdale Avenue
5261 Carnegie Street Lysle Street at A Street
807 Leydon Street 929 Kirkbride Street
5268 Wickliff Street 713 Melrose Avenue
5222 Wickliff Street  

 

 

work is weather-dependent and subject to change

Locations & Schedule

Location Details:
Throughout service area

Start Date: Ongoing

Completion Date: Ongoing, with pauses during cold weather

Work Schedule: 7:00 am - 5:00 pm, M-F

Traffic Patterns: Street closures and no parking may be necessary to complete paving work.

Project Contacts

If you have questions, please contact

Construction Communications Project Manager :
Mora McLaughlin

mmclaughlin@pgh2o.com