After we complete a water or sewer repair, we must then come back and repave or re-concrete the area we impacted as part of our work. This multi-million dollar effort improves streets and sidewalks throughout our service area as a result of our work underground.
We are responsible for asphalt and concrete replacement after emergency water and sewer repairs or infrastructure upgrade projects. When a job is complete, the location is given to the restoration contract, which sends asphalt, concrete, and line painting crews out to restore the area to its former condition. When work happens on your street, it may be a few weeks until paving and concrete crews return. Crews move in an orderly fashion around our service area completing work, focusing on all the locations in one area before moving onto the next.
Percentage completion on this project refers to the total number of sites addressed as part of this construction contract and does not reference to the total number of PWSA restoration sites completed over time.
Progress & Status
The street and sidewalk restoration locations for July 2nd are as follows:
Addison Street at Hemans Street | 4267 Stanton Avenue |
27 McCandless Avenue | 5014 Stanton Avenue |
118 N. Mathilda Street | 970 Oramore Street |
4913 Dearborn Street | 5155 Hillcrest Street |
5223 Jordan Way (On Kincaid Street) | Alpine Street at Arch Street |
5170 Hillcrest Street | 258 Carrington Street |
322 Azure Street (Rear on Schenley Manor Drive) | 1012 Abedll Street |
5143 Rosecrest Drive | 1102 Galveston Street |
5168 Rosecrest Drive | N. Franklin Street at Bidwell Street |
265 Schenley Manor Drive | 915 Behan Street |
956 Oranmore Street | 1118 Decatour Street |
959 Oranmore Street | 1336 Pennslyvania Avenue |
970 Oranmore Street | 2034 Chateau Street |
146 44th Street | 1501 Preble Avenue |
5248 Carnegie Street | Reedsdale Street at Scottdale Avenue |
5261 Carnegie Street | Lysle Street at A Street |
807 Leydon Street | 929 Kirkbride Street |
5268 Wickliff Street | 713 Melrose Avenue |
5222 Wickliff Street |
work is weather-dependent and subject to change
Locations & Schedule
Location Details:
Throughout service area
Start Date: Ongoing
Completion Date: Ongoing, with pauses during cold weather
Work Schedule: 7:00 am - 5:00 pm, M-F
Traffic Patterns: Street closures and no parking may be necessary to complete paving work.
Project Contacts
If you have questions, please contact
Construction Communications Project Manager
:
Mora McLaughlin
mmclaughlin@pgh2o.com