In Planning
Water
PWSA will work in portions of Esplen to replace all lead service lines found with a non-lead material.
Progress & Status
Design Complete
Crews will begin inspecting service lines within the project area in July 2023
Locations & Schedule
Location Details:
Esplen
Start Date: July 2023
Completion Date: September 2023
Work Schedule: Monday-Friday, 7:00 a.m. - 5:00 p.m.
Traffic Patterns: Street closures will be posted throughout the project area as needed.