Lead Service Line Replacement Project - Allentown

In Construction Water

PWSA will work in portions of Allentown to replace all lead service lines found with a non-lead material.

Progress & Status

5%
Construction Complete

Crews are beginning service line verification and limited lead service line replacements.

Locations & Schedule

Start Date: Summer 2024

Completion Date: Fall 2024

Work Schedule: Monday-Friday, 7:00 a.m. - 5:00 p.m.

Traffic Patterns: Streets will be closed to traffic during working hours and will be reopened at the end of a work day.