In Construction
Water
This project, in Millvale Borough, will replace portions of water mains on several streets, providing more reliable water service to our customers.
Progress & Status
Construction Complete
- Clara Street - work is complete, street and sidewalks will be restored
- Beckert Street - work is complete, street and sidewalks will be restored
- Van Buren Street - work is complete, street and sidewalks will be restored
- Siegel Street - work is complete, street and sidewalks will be restored
- Davis Street - service line installation in progress
- Lippert Street - work is complete, street and sidewalks will be restored
- Lincoln Avenue - service line installation in progress
- Sherman Street - service line installation in progress
- Grant Avenue - service line installation in progress
- Sheridan Street - service line installation in progress
- Fornoff Street - work is complete, street and sidewalks will be restored
Locations & Schedule
Start Date: Summer 2023
Completion Date: Summer 2024
Work Schedule: Monday – Friday from 7:00 a.m. – 5:00 p.m.
Traffic Patterns: The street will be closed to local traffic during working hours and will be plated and re-opened at the end of the work day.